RELOCATE ALL PROTECTION & CONTROL
FROM EXISTING POWER PLANT CONTROL ROOM TO NEW SUBSTATION CONTROL HOUSE
Powerserve Technologies is currently relocating all protection & control functions at the Marathon Substation from the power plant control house to the new substation control house. This project included the careful installation of new cable trench inside the energized substation yard for the installation of all new control cable. In addition, the protection for the two transmission lines will be moved to the new control house without a line clearance. Currently, relay panels are installed and tested. Distribution protection is scheduled to be moved to the new control house in June with transmission lines to follow.